Close a Contract

Contract close out is the process for closing out contract obligations and liabilities with suppliers. In P2i, a contract commences the process when an email notification is received by the P2i Contract Officer signalling the end date is approaching or a contract has expired and requires closing.

Warning This process is not the termination contract close out procedure. Refer to Terminate a contract.

P2i expires contracts on the contract's end date.

Note An archived contract must first be restored before the contract close out process can commence. Contact P2i Technical Support requesting the contract be restored - refer to Support.

Close a Contract - Process Overview

Every contract in P2i is created within a procurement project (i.e. a container for all Go To Market and Contract set up activities). When a contract is being closed it is necessary to close it in the procurement project where it was created. This requires the P2i Contract Officer to complete workflow tasks with a status of running in the project's workflow processes.

The close out process is commences in P2i's Main Dashboard by the P2i Contract Officer after receiving a P2i email notification (i.e. a reminder alert) informing a contract is due to expire and requires close out. The activities will focus on the project and its workflow tasks.

The close out process will require the P2i Contract Manager (or P2i Regional Manager) to proceed to the Downstream Dashboard and close the contract. The contract's closure may occur many months after the contract has expired due to:

  • no further reporting obligations being required

  • no further payments being made.

The final stage of the close out process occurs in the P2i's Main Dashboard where the P2i Contract Officer or P2i Contract Manager closes incomplete or not started workflow tasks remaining in the procurement project.

In the overview diagram:

  • - is the procurement project including its workflow tasks

  • - is the contract.

close a contract workflow diagram

The contract close out process utilises a predefined sequential approval list located in the project's Project Approver List - Contract Closeout Approver/s. This predefined list is a convenience for the P2i Contract Officer to request approval to close out a contract rather than manually choose the approver/s.

This step is optional. The setup of the approver list may have been completed earlier during contract setup. It is performed by the P2i Senior User.

The P2i Contract Officer receives an email notification (i.e. a reminder alert) informing a contract is due to expire and requires close out. The timing and frequency of sending reminder alerts is chosen when the contract is first created. The sending of reminder alerts are updated to suit contracting team preferences. Refer to Set the Send Reminder Alert, who you want the alert to go to, and the Days before Contract Expiry Date.

Tip P2i users can run reports or create charts that are visible on their main dashboard to expiring contracts within certain time-frames. Users can also run a search on their "My Contracts" list to see which contracts are expiring and when.

For shorter in length contracts (e.g. 1-3 months), the P2i Contract Officer must run a report listing these contracts.

The P2i Contract Officer will complete the Manage Contract workflow task. This moves the contract to the next project workflow task - Prepare contract close out & send approval where the P2i Contract Officer attaches relevant documentation and requests approval to close out the contract.

This step is the recording of the approval within in the Prepare contract close out & send approval workflow task by the approver/s listed to close out a contract.

Once the approval is provided, the workflow Prepare contract close out & send approval will be Completed automatically by P2i and will update the workflow Close contract to Running.

Note In the scenario where there are multiple approvers listed, the approvals are actioned in the respective order they are listed.

The first approver will receive an email notification requesting their approval. They provide their approval.

The second approver listed will receive an email notification after the first approver has provided their approval.

The workflow will then follow the same behaviour as if only one approver was listed.

Approval is granted from approver/s. The P2i Contract Officer promotes the contract from the now Completed workflow to the next workflow - Close contract.

Note P2i expires a contract on the contract end date.

The P2i Contract Manager (or P2i Regional Manager) closes contract in the Contract Management Hub:

  • AFTER the contract has expired

  • AFTER all reporting obligations (including performance based or financial acquittals) are fulfilled.

Note Closing a contract may occur several months after the contract has expired.

This step is performed in P2i's Main Dashboard by either the P2i Contract Officer or P2i Contract Manager.

All remaining incomplete or not started workflow tasks are actioned so the procurement project is updated from Running to Completed.

Note Follow your Department's recordkeeping practice and procedures to store documentation related to this contract close out process.